Capacity |
2 x 600 MW Sub – Critical Units with River Water Intake System |
Location |
Chhattisgarh, India |
Contract Duration |
38 Months |
Contract Value |
INR 2952.26 Crores (US$ 454.65 Millions) (1 US$=INR 65) |
Project Status |
Work in progress, expected commissioning March 2016 |
Design,Engineering, Procurement, Construction to Handing Over. |
Complete Designing, Engineering, Manufacture, Supply, Erection, Testing & commissioning of Balance of Plant (BOP) including associated Civil, Structural, Mechanical, Electrical, Instrumentation, etc. |
Erection, Testing & Commissioning |
Boiler, Turbine, Generator (BTG) & Auxiliaries. |
Civil & Structural Works |
Turbine-Generator building, Mill & Bulker Bay, ESP & Fabric Filters. |
Coal handling Plant (Track hopper, Wagon Tippler, Bunkers, Conveyor galleries, Crusher House, Transfer House / Junction Towers, Coal Handling Plant Control room building, Pump House for DS system, Tunnels, Dust Suppression, extraction and ventilation system, Coal settling Ponds, Coal Stockyard, Stacker cum Reclaimer foundations, Crusher foundations). |
|
ESP Control room Building, Air Washer room Building, Central Control / equipment room building, Electrical switch Gear Building, RCC Chimney 275m high, Air Conditioning System building, Ventilation system building |
|
Ash Handling Plant including (Bottom ash hopper, Bottom ash slurry pump house, Ash Water Pump house, Ash slurry pipe supports, Ash handling Hydro bins, Ash pond and associated works, HCSD Pump house, HCSD pipe supports, Compressor House, Vacuum Pump House, Recirculation Pipe Supports, Fly ash silo and paving in silo area, Silo area utility building, MCC and control room for entire ash handling plant). |
|
Water System Including (Water retaining structures, CW Pump House with fore bay including CW and ACW pumps foundations and structural steel superstructure housing EOT/Gantry Crane, CW Fore bay/desalting basin, Silt flushing Pump house, Stop log gates, Trash rack/screens, CW intake and discharge duct work/RCC channel, Laying of CW pipe from CW pump house to Turbine building, Turbine building to cooling tower to CW pump house fore bay, Neutralization pit, Chlorination building, Central Monitor basin, Cooling tower, DM Plant building, Chemical House, DM Water tanks and CST Tanks, Service Water Storage tanks & pump house, Potable water storage tanks, Effluent Treatment plant and guard pond, Ash Water recirculation system building, Water Supply System, CW Chemical dosing pump house, Sewerage treatment plant & Effluent treatment Plant, Auxiliary cooling Water pump house, pump & Equipment). |
|
Fire Protection System (Fire Water pump house , Fire protection system buildings) |
|
Fuel oil handling system (Fuel Oil Pump House, Fuel Oil Tank farm area, Fuel Oil Tanks and fuel oil Dyke, Fuel Oil Unloading facilities). |
|
Compressed Air System (Compressor house for main plant compressor & Electrostatic Precipitator (ESP) compressor, Instrumentation and Services air compressor house building). |
|
400 kV Switchyard, Cable trenches and pipe trenches, Transformer yard Service Building, Work Shop Building, Railway track in transformer yard Boiler Elevator Supporting Structures, Belt Conveyors for bottom ash handling system, Ash handling control rooms & buildings. |
|
Infra Works |
Residential Colony, Shopping complex, Ash Pond/ Dyke, Club house, Covered car parking, Servant quarters, Community center, Amphitheatre, Raw/River Water Intake System Overhead Transmission Line. |
Mechanical, Electrical, Instrumentation Works for (BTG & BOP) |
Design, manufacture, supply, transportation, storage, erection, testing and commissioning of Balance of Plant (BOP) and erection, testing & commissioning of Boiler, Turbine & Generator (BTG) and Auxiliaries. |